Spring/summer 2027 range planning means fixing your SS27 home storage assortment, shelf dates and purchase orders before the season opens. For a European retailer it is a scheduling decision as much as a buying one, because the calendar is fixed: shelf date minus 96 to 141 days equals the day the order has to be confirmed. A KingwayHome order needs 7–15 days for samples, 45–60 days for production, then 30–45 days in transit and 7–14 days to a DC slot. Confirm later than that and the next production window sits after Chinese New Year on 6 February 2027.
Range reviews usually open with product selection and end in a scramble over delivery dates. Reversing the order costs nothing and removes most of the risk. Write the shelf date first — the week the SS27 set has to be merchandised, photographed and live in the webshop — then subtract every stage that cannot be compressed.
| Sample round | Stock sample or custom sample shipped to your office | 7–15 days |
| Sample approval and PO | Feedback, revision or sign-off, order confirmation | 3–7 days |
| Production | Material preparation, production run, packing, pre-shipment inspection | 45–60 days |
| Ocean freight | Port handling, sailing to a European port, customs clearance | 30–45 days |
| Inland and DC booking | Haulage, unloading, booking into your distribution centre calendar | 7–14 days |
| Total | From sample request to goods on shelf | 92–141 days |
That is roughly three to four and a half months. A shelf date in the first week of March 2027 puts the sample request in November 2026 and the confirmed PO before the first week of December 2026. A shelf date at the end of April 2027 moves both dates forward by about seven weeks.
Spring assortments in European home and living retail follow a fairly predictable shape, and knowing the shape helps you decide which items have to be on the water first.
Chinese New Year falls on 6 February 2027, and the disruption is wider than the holiday itself. Production winds down in the last week of January as workers travel, most lines stop for two to four weeks, and capacity returns to normal only in early March. Add pre-holiday freight congestion — exporters push shipments out three to four weeks before the break — and the practical conclusion for European buyers is that the last comfortable shipping window for SS27 goods is the first half of January 2027.
Two consequences matter when you build the plan:
Anything confirmed after mid-January 2027 should be planned as a May or June arrival. Treating that as a planning rule rather than a surprise is what keeps an SS27 set complete instead of 80% complete.
The one-line rule: if the goods have to be on shelf before mid-April 2027, the PO has to be confirmed in 2026. If it is not confirmed by mid-January 2027, plan the arrival for May.
The calendar below is the sequence we work through with buyers on a mixed SS27 programme. Dates assume FOB with a European DC delivery and a standard 45–60 day production slot.
| November 2026 | Request samples for the spring reset block. Approve materials, colours and packaging direction. Confirm POs for any item that has to land before mid-March 2027. |
| December 2026 | Confirm POs for April landings. Lock artwork and label copy. Book the pre-holiday production slot and the sailing before freight space tightens. |
| January 2027 | Ship everything that is ready. Do not open a new production slot in the second half of the month — it will not finish before the break. Move unconfirmed items to the post-holiday queue on purpose. |
| February 2027 | Production pause. Use the window for SS28 concept work, spec sheets and photography briefs rather than chasing confirmations. |
| March 2027 | Capacity returns. Place replenishment orders for items that sold through in the reset, and summer top-ups that can land in June. |
| April–May 2027 | Late top-ups only. At this point the decision is between waiting for a June sailing and paying for air or rail on a small, high-value subset. |
Lead time is only half of the schedule. The other half is the list of decisions that cannot be made after production starts, and each one has a quiet cost when it slips.
| Storage racks and shelving | Powder-coat colour matching and load-rating checks add a sample round. Start these first if the range has a custom finish. |
| Fabric storage and laundry | Dye lots and print repeats need approval against a physical sample. Confirm before the holiday, because a dye-lot change after restart costs another sample cycle. |
| Woven baskets | Handwoven in Southeast Asia, so capacity is booked rather than switched on. Larger programmes need to be placed earlier than metal or fabric. |
| Pet carriers and cat furniture | Production is rarely the constraint; volume is. Bulky cartons consume container space, so book freight early and check the carton cube before you finalise quantities. |
| Private label programmes | Add one to two weeks for artwork, labels and packaging proofs on top of the standard schedule. |
The retailers who avoid the January panic do three unglamorous things. They put the shelf date and the calculated PO date in the same document as the product list, so a late approval shows up as a late delivery before it happens. They approve samples in November for anything that has to land before mid-March. And they split the programme: a core order that ships before the holiday, and a smaller replenishment order that ships in March for the items that always sell through.
If you are building an SS27 set now, the sequence to follow is straightforward: read the materials guide for European retail to fix the material direction, check the storage racks wholesale range and the new pet carriers and cat furniture wholesale page for the two blocks that need the earliest dates, then send us your shelf dates through the contact page. We will come back with a calendar that shows which items make February, which make April, and which should wait.
For a shelf date before mid-March 2027, confirm the order by the first week of December 2026. For an April landing, confirm by early January 2027. The calculation is shelf date minus 96 to 141 days, which covers samples, production, ocean freight and DC booking.
Production runs 45–60 days after sample approval, and ocean freight to a European port takes a further 30–45 days, with 7–14 days for inland haulage and DC booking. Samples themselves take 7–15 days.
Yes, if they are meant to ship in February. Production winds down in the last week of January 2027 before the holiday on 6 February, and capacity returns to normal in early March, so December orders should be planned to sail by mid-January.
Yes, and for mixed ranges it is usually the better plan: a core order that ships before the holiday and a smaller replenishment order that ships in March. Both can be confirmed together so the production slots are reserved.
MOQ starts from 200 pcs per item, with 200–1,000 depending on item and customisation. Mixed-item orders across categories are welcome, which makes it possible to build a coordinated set without committing to a large quantity per SKU.